Indication about every step of installation process, which should be followed one step by one step:
-1. All steel columns need to assembled on the foundation with anchor bolts. Checking and measuring all columns to make sure that all columns parallelized in the same line.
-1.所有钢柱都需要用地脚螺栓组装在基础上。 检查和测量所有列以确保所有列平行于同一行。
-2.Connecting all columns with tie rod.
-2.用拉杆连接所有柱子。
-3.Steel beams are pre-assembled under ground, then lifting up to assembled with steel columns together.
-3.钢梁在地下预先组装,然后吊起与钢柱组装在一起。
-4.All beams are connected together with tie rod.
-4.所有横梁用拉杆连接在一起。
-5.Roof purlines with bracing
-5.带支撑的屋顶檩条
-6.Roof panels
-6.屋顶板
-7.Wall purlins with bracing
-7.带支撑的墙檩条
-8.Wall panels
-8.墙板
-9.Brick wall
-9.砖墙